3rd Party DEP Reports

These reports are required by the DEP and have been made by an independent 3rd party. They have been posted here as a service to the community.

3PI Observations 051810

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Tuesday, 05-18-10 Time: 7:30-1:30 PM Report: 26
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: 50, Sun
General Contractor: Reed & Reed Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating
Contacts onsite: no one
Date of Last Inspection: 01-14-10

3PI Observations 011410

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Thursday, 01-14-10 Time: 8:00-9:30 PM Report: 25
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: 20, Sun
General Contractor: Reed & Reed Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating
Contacts onsite: Ray (Reed+Reed), Chris (Sargent), Tracy (Sargent)

3PI Observations 010510

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Tuesday, 01-05-10 Time: 8:00-9:30 PM Report: 24
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: 20, Overcast
General Contractor: Reed & Reed Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating
Contacts onsite: Ray (Reed+Reed), Dan, Tracy (Sargent)

3PI Observations 122809

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Monday, 12-28-09 Time: 8:30-10:30 PM Report: 23
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: 25, sun
General Contractor: Reed & Reed Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating
Contacts onsite: Ray (Reed+Reed), Dan, Tracy (Sargent)

3PI Observations 122209

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Tuesday, 12-22-09 Time: 7:30-9:00 PM Report: 22
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: 15, 15 mph wind, sun
General Contractor: Reed & Reed
Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating

3PI Observations 121709

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Thursday, 12-17-09 Time: 8:00-10:30 PM Report: 21
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: -6, 25 mph wind, very cold!
General Contractor: Reed & Reed Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating

3PI Observations 121009

DEP Project #: L-24441-24-A-N/L-24441-TF-B-N
Date: Thursday, 12-10-09 Time: 8:00-11:00 PM Report: 20
Observed by: Steve Roberge, PE Company/Agency: SJR Engineering Inc.
Weather Conditions: 30s, Overcast, cloudy
General Contractor: Reed & Reed Civil Site Contractor: Sargent
Clearing Contractor: DGD Trucking/JML Trucking & Excavating